Question 1
A federal dredging contract incorporates FAR 52.236-2. Excavation exposes a buried rock ledge that differs materially from the soft sediment indicated in the contract's borings. There is no immediate safety hazard, and another authorized reach can be worked without disturbing the ledge. What should the contractor do next?
Show answer & explanation
Correct answer: D - Notify the Contracting Officer promptly in writing, preserve the ledge, and continue in the other authorized reach.